Execution of the project

Terms of execution

Start: 31st December 2008
End: 31st December 2010

Timetable

1. Stage (month 1 to 6)

Start of the project

  • creation of plan and timetable of individual stages,
  • study of supporting material (current security projects and internal regulations),
  • discussions with security management staff,
  • preparation of forms for facility assessment.

2. Stage (month 7 to 11)

Evaluation of current state of protection of the most important facilities of electricity networks

  • assessment of the level of physical protection in the Czech Republic and those of the foreign partner,
  • accomplishment of security risk analysis with respect to physical protection of network facilities,
  • identification of critical points in protection of selected electricity network facilities.

3. Stage (month 12 to 20)

Proposal of standard and methodology

  • proposal of security standards for protection of energy network facilities,
  • proposal for methodology for assessment of security of targets including estimated implementation costs of minimal security standards.

4. Stage (month 20 to 24)

International conference – theme: Physical protection of selected electricity network facilities

  • conference preparation,
  • conference,
  • outputs summary,
  • presentation of project results,
  • evaluation of the project.